• 22597340
  • 87216931
  • This email address is being protected from spambots. You need JavaScript enabled to view it.
  • L-V de 8:00 a.m. a 3:00 p.m.
Ministry of Health Procedures

Wastewater Treatment System Siting Approval

Geo Costa Rica assesses the property, proposed system location, setbacks, water bodies, wells, and treated effluent disposal options to prepare and manage the Siting Approval application before the Ministry of Health.

Assess the location Before finalizing the system design
Evaluate the surroundings Property, setbacks, water bodies, wells, and final disposal
Prepare the application Mapping, documentation, and follow-up with the Ministry
A decision to make before detailed design

What is the Siting Approval for a treatment system?

This is the procedure through which the Ministry of Health assesses the proposed location of a wastewater treatment system within a project and the surrounding land-use conditions.

The purpose is not yet to approve the complete construction design of the plant, but to verify that the location designated for the system can be assessed in the context of the overall project and its surroundings.

The assessment considers the proposed location, preliminary dimensions, setbacks, buildings, water bodies, water supply wells, and the intended final disposal method for treated wastewater.

First, determine whether the procedure applies

Does my project require Siting Approval?

Not all sanitation systems necessarily follow the same procedure. The type of system, flow rate, final disposal method, and project characteristics must first be reviewed.

System

What sanitation solution is proposed?

Determine whether the project proposes a treatment plant, an individual system, disposal through drainage, or another sanitation solution.

Flow rate

How much wastewater will be generated?

The system flow rate and projected water consumption are relevant in determining the applicable regulatory procedure.

Disposal

Where will the treated effluent go?

Infiltration, sewerage, receiving water body, reuse, and other options may involve different technical and institutional requirements.

Current Ministry guidance identifies this procedure for systems with influent flows greater than 5 m³/day and also specifies conditions for disposal through drainage when actual or projected drinking water consumption exceeds 190 m³ per month.

Determine the site first

Review the location before completing the system design

A technically well-designed system can still cause problems if it is located in an area incompatible with setbacks, buildings, surface water, wells, or the intended final disposal method.

Professionals reviewing the proposed wastewater treatment system location during a site visit

Geo Costa Rica examines the proposed location within the property to identify potential conflicts that should be resolved before proceeding with construction drawings and other project investments.

  • Available space for the system.
  • Relationship to property boundaries and buildings.
  • Topography and site configuration.
  • Water bodies and drainage features.
  • Nearby water supply wells.
  • Proposed treated effluent disposal option.
  • Access and relationship to the rest of the project.

Changing a location during the conceptual stage is generally much easier than doing so after detailed design is complete.

The treatment plant is part of its surroundings

What do we assess on the site?

The system location must be understood within the entire project, not as an isolated installation placed in whatever space remains.

We combine field inspection, drawings, mapping, and spatial analysis to determine how the system relates to the property and its immediate constraints.

  • Property boundaries and geometry.
  • Proposed system location.
  • Preliminary dimensions.
  • Existing and proposed buildings.
  • Access and circulation areas.
  • Slopes and surface drainage.
  • Existing infrastructure.
  • Relevant environmental conditions.
Technical inspection of a wastewater treatment system and site conditions
Having enough physical space is not sufficient

Setbacks and the system's relationship to the project

The site plan must show how the proposed system area relates to boundaries, buildings, and other relevant project features.

Property

Boundaries

The location must allow identification and measurement of setbacks between the treatment system and the property boundaries.

Project

Buildings

The relationship to existing or proposed buildings on the same property must also be shown.

Operation

Access and functionality

In addition to spatial requirements, the location must be functional for future operation, inspection, and maintenance.

Protecting water resources

Wells, groundwater, and hydrogeological constraints

Nearby water abstraction points must be included in the assessment to understand the relationship between the proposed system and water resources.

Professionals reviewing maps, water bodies, wells, and site constraints for a project

The Siting Approval documentation must identify existing or proposed water supply wells within the property and certain nearby abstraction points.

The current procedure also requires identifying existing water supply wells on adjacent properties within a radius of 100 meters from the treatment plant.

Where project conditions warrant, Geo Costa Rica can expand the assessment to include hydrogeological information, aquifers, springs, and other sensitive features to better understand the feasibility of the proposed sanitation solution.

Surface water and drainage

Water bodies and site drainage

Streams, rivers, and other drainage features can affect both the system location and the selected option for treated effluent disposal.

Identification

What water bodies are present?

We review mapping, the site, and available records to identify water features that may be relevant to the project.

Flow

Where does the site drain?

The plan must show the flow direction of water bodies that cross or border the property.

Destination

Will the effluent be discharged into a receiving water body?

If the proposed solution involves discharge into a receiving water body, the Water Directorate's applicable procedures must also be reviewed.

The plant's responsibility does not end at the treatment outlet

Where will the treated wastewater ultimately go?

The Siting Approval requires identifying and justifying the proposed final disposal option for the effluent.

Sewerage

Connection to a sewer system

Where a sewer network is available, the feasibility and conditions for conveying treated effluent into that system must be assessed.

Subsurface

Infiltration into the ground

Disposal through infiltration requires an evaluation of soils, hydrogeological conditions, and any other applicable project requirements.

Receiving water body

Discharge of treated wastewater

Where the effluent will be discharged to a receiving water body, the applicable conditions and authorizations under the discharge regulations must also be met.

Other options

Final disposal must be determined case by case

The regulatory framework also provides for alternatives such as reuse, submarine outfalls, or evaporation when technically and legally applicable.

Geo Costa Rica reviews the project circumstances before determining the appropriate institutional procedure.

Site + water + mapping + administrative support

How does Geo Costa Rica handle Siting Approval?

We integrate the site's territorial assessment with project information and the proposed sanitation solution.

01 · Review Project, property, and existing records.
02 · Verify Whether this procedure applies to the project.
03 · Inspect Location and site conditions.
04 · Map System, boundaries, water features, and relevant elements.
05 · Assess Setbacks and territorial constraints.
06 · Define The proposed final effluent disposal approach.
07 · Compile Plans, documents, and the application file.
08 · Manage Submission and follow-up with the Ministry of Health.
Institutional assessment

What does the Ministry of Health assess?

The Ministry reviews the submitted information to determine whether the requested Siting Approval should be granted.

Project

General characteristics

The overall project, location, owner, activity, and general characteristics of the proposed system are identified.

Location

Placement within the property

The proposed area, preliminary dimensions, setbacks, and relationship to other elements shown on the site plan are reviewed.

Effluent

Final disposal

The intended final disposal method for treated wastewater must be identified and technically justified.

Geo Costa Rica does not guarantee that Siting Approval will be granted. We prepare and support the application technically; the Ministry of Health conducts the assessment and issues the corresponding decision.

Siting is an earlier stage

What happens after obtaining Siting Approval?

Siting Approval allows the project to proceed to subsequent stages, but does not constitute comprehensive approval of the system's construction design.

01 · Siting The applicable Siting Approval is obtained.
02 · Design The final design is developed or adjusted.
03 · Drawings The corresponding construction drawing approval process follows.
04 · Construction Construction proceeds in accordance with applicable drawings and permits.
Construction drawing approval

Detailed construction design follows a separate procedure

The Ministry of Health has a specific procedure for Approval of Construction Drawings for Wastewater Treatment Systems, processed digitally through the CFIA APC platform.

Initial review

What information do we need to get started?

We can conduct a preliminary review of the proposed location even if the system design is not yet complete.

Property

Site

  • Cadastral survey plan.
  • Property location.
  • Property area.
  • Available property registration information.
Project

Proposed development

  • Available site layout.
  • Project use.
  • Expected capacity or population.
  • Preliminary system location.
Sanitation

Proposed solution

  • Proposed system type.
  • Estimated flow rate.
  • Proposed final disposal method.
  • Existing studies or background information.
From site selection to official decision

How do we approach Siting Approval?

The process aims to identify conflicts early and propose a location that is technically compatible with the project.

01 · Project Review the site and proposed sanitation solution.
02 · Applicability Confirm the appropriate institutional procedure.
03 · Fieldwork Verify relevant site conditions.
04 · Assessment Review location, water, setbacks, and disposal.
05 · Mapping Prepare the spatial documentation supporting the application.
06 · Application file Compile the required documentation.
07 · Submission Submit the application to the Ministry of Health.
08 · Follow-up Respond to requests within our professional scope.
Frequently asked questions

Questions about treatment system siting

Answers for projects that must determine where to locate their system before proceeding with design.

What is Siting Approval from the Ministry of Health?

It is the procedure through which the Ministry assesses the proposed location of a treatment system within a project before subsequent construction-related stages.

Should it be requested before the plant design is completed?

Yes. Its purpose is to assess the location before the subsequent construction drawing approval process, helping identify spatial conflicts early.

What does Geo Costa Rica review before submitting the application?

We review the site, proposed location, project, setbacks, water bodies, wells, maps, and the intended treated effluent disposal option.

Must nearby wells be identified?

Yes. The procedure requires showing wells on the property and existing water supply wells on adjoining properties within the applicable institutional radius.

What is the radius for wells on adjoining properties?

Current Ministry guidance specifies a radius of 100 meters from the treatment plant for existing water supply wells on adjacent properties.

What if there is a stream or river nearby?

It must be included in the assessment and maps. If effluent is discharged into a receiving water body, other institutional procedures may also apply.

Can the plant discharge into the ground?

Infiltration may be an option in some cases, but applicable technical, sanitary, and hydrogeological conditions must be met.

Does Siting Approval replace the Wastewater Discharge Permit?

No. If treated wastewater is discharged into a receiving water body, the corresponding Water Directorate procedure must also be assessed.

Does Siting Approval approve the construction drawings?

No. The Ministry has a separate subsequent procedure for Approval of Construction Drawings for Wastewater Treatment Systems.

How long does the Ministry of Health take?

Current institutional guidance indicates a period of 22 calendar days to issue a decision. This institutional period should not be confused with the time required to prepare information or address possible requests for additional documentation.

How long is Siting Approval valid?

Current institutional guidance establishes a validity period of two years from the date of issuance.

Does Geo Costa Rica design the treatment plant?

Geo Costa Rica focuses on territorial assessment, hydrogeology, mapping, final disposal, and institutional procedures. When a project requires sanitary, hydraulic, or electromechanical design subject to specific professional responsibilities, that component must be prepared by a suitably qualified professional.

The disposal method determines the next procedures

Related studies and procedures

The next steps depend on how the project's wastewater will be treated and where it will ultimately be disposed of.

Wastewater

Wastewater Treatment Systems

We assess the project's sanitation solution and the institutional procedures related to treatment and final disposal.

AyA

Sanitary Sewer Exemption

For certain residential projects where the sanitation solution requires hydrogeological studies, infiltration tests, and contaminant transport analysis.

Water Directorate

Wastewater Discharge Permit

Applicable where treated wastewater is discharged into a receiving water body regulated under the discharge regime.

Siting Approval

Do you already know where you want to locate the treatment system?

We can review the site, proposed location, water bodies, wells, setbacks, and disposal option before the project proceeds too far with a location that could create conflicts.

Send us the cadastral survey plan, site layout, and available system information. You do not need a completed construction design for an initial review.

01
We assess the property Project, space, and constraints.
02
We evaluate water resources Wells, water bodies, and disposal.
03
We prepare the maps Location, setbacks, and relevant features.
04
We manage the Ministry procedure Application file and technical follow-up.